In Operation

Yaentu MHPP

Yaentu project is a run-of-river hydropower plant located in the city of Poso, Central Sulawesi with the installed capacity of the plant is 10.0 MW. Construction began in December 2020 and Yaentu project has passed the commissioning process on October 2024 complying with the contract and is declared ready for operation after successfully completing reliability testing for both turbines over a period of 3x24 hours. Thus, the Yaentu project becomes the third power plant to operate under ARKO, with the largest estimated electricity production, around 62,476 MWh per year.

Detail Project

Capacity

10 MW

Status

In construction

Location

Central Sulawesi

Net Head

165 Meter

Turbine Type

Horizontal Francis Turbine

Turbine Manufacture

-